Projects

Named plants, real vessels, and the time each one actually took. Every figure below comes from our own job record.

The record, in numbers.

87

Jobs in the log since 2018

69

Plants and authorities served

19

States worked

41

Digester cleanouts

Projects

Featured projects.

Five jobs we photographed. Durations come from the start and end dates logged at the time, not estimates. The other eighty-two are in the record above.

Friedens, Pennsylvania
The Crawler on an agricultural manure lagoon
Vessel
Manure lagoon
Duration
Agitation
Visits
March 2023
Fort Wayne, Indiana
Digesters cleaned across a full winter, 500 miles out
Vessel
Anaerobic digesters
Duration
173 days on site
Visits
September 2023
Strattanville, Pennsylvania
Two lagoons dewatered, and a baffle installed
Vessel
2 treatment lagoons
Duration
59 days on site
Visits
April 2021
Towanda, Pennsylvania
A 122-day tank cleanout in the Susquehanna valley
Vessel
Tanks
Duration
122 days on site
Visits
October 2025
Canandaigua, New York
The same digester, before and after
Vessel
Anaerobic digesters
Duration
28 days, then 23
Visits
March 2023 and June 2024

Got a vessel like one of these?

Dimensions, rough volume, and how long since the last cleanout. That’s enough for scope, a window and a price.