Digesters cleaned across a full winter, 500 miles out

Fort Wayne Water Pollution Control Plant, Fort Wayne, Indiana — Nearly six months in Indiana, running from September through the winter.

Vessels
Anaerobic digesters
Duration
173 days on site
Started
September 2023
Client type
Municipal authority
The situation
Multiple digesters at a large midwestern plant, roughly 500 miles from the Somerset yard. At that distance there is no local depot to fall back on — everything that rolls in has to keep running for the duration.
What we did
The site photograph shows the spread on arrival: an MSS mixing tank with integrated access platform and railing, suction lines run out, and one of our own tractors alongside. Full drawdown, on-site dewatering, confined-space cleaning and disposal followed, with our own generators supplying site power rather than tying into plant service.
The outcome
173 days on site, September 2023 through to the following spring — one crew, one schedule, and the same equipment on the pad from the first day to the last.
Service
This job ran under Digester cleaning. Working a vessel like this one? Send us dimensions and rough volume and we will tell you what the job takes.
On arrival
MSS mixing tank with access platform, suction lines run, tractor alongside.

Other projects.

Friedens, Pennsylvania

The Crawler on an agricultural manure lagoon

Wayne Martin’s Farm, Friedens, Pennsylvania — The same surface-operated equipment that works municipal lagoons, on

Strattanville, Pennsylvania

Two lagoons dewatered, and a baffle installed

Strattanville Borough Municipal Authority, Strattanville, Pennsylvania — Dewatering of two lagoons for a borough authority,

Towanda, Pennsylvania

A 122-day tank cleanout in the Susquehanna valley

Towanda WWTP, Towanda, Pennsylvania — The longest tank job in our record, and the most